owner
City of Allen
estimated completion date
completion date
Q2 2027
scope
Two lift station rehabilitations including demolition of existing pumps, pipe & valves, odor control and wet well lining. All demoed materials and equipment to be replaced in-kind, including additional electrical upgrades. These lift stations are critical to the Cities infrastructure, as such, each lift station will require bypass pumping and all rehabilitation work will need to be completed in a 14-day shutdown window.
contract price
$4,300,000