WWTP Rehabilitation Project A-1
[IN PROGRESS]Treatment

WWTP Rehabilitation Project A-1

Clarifier rehabilitation and process equipment replacement at a regional wastewater treatment plant.

WWTP Rehabilitation Project A-1

Owner

City of Cleburne

Estimated Completion Date

Q3 2026

Location

Cleburne, TX

Scope

CLW is responsible for dewatering the existing clarifier and aeration basins, removing any remaining sludge and demolishing the old equipment. After making the necessary repairs to the existing concrete basins, a new clarifier mechanism, new weirs & baffles and new fine bubble diffusers are installed, tested and brought online.

Contract Price

$4,300,000